>Departments > Road & Bridge > Flood Response/Repair Information

Flood 2013 Response/Repair Road Information

Progress to Date

Road number
Road name
From To Planned project end date Work accomplished to date Current road condition Closure type Last updated
22H
CR 22H (Part 1)
US 34 9597 CR 22H Minimal damage and debris from initial flood removed from road surface and right of way. All-weather surface Restricted Access Only 06/17/14 8:22 AM
22H
CR 22H (Part 2)
9597 CR 22H CR 29 Local access established to hard closure at 9597 CR 22H. Pioneered single lane Full Closure 06/17/14 8:23 AM
27
CR 27 (Buckhorn/Stove Praire Rd)
18000 Buckhorn Rd Ohana Way No work started on this portion of road. For Project Summary information: http://larimer.org/engineering/PROJECTS/Stat9323.htm or Newsletter: http://larimer.org/engineering/cr_27.pdf Full Closure 09/29/14 7:34 AM
29
CR 29
approx. 1 mile north Hwy 34 approx. 2 miles SW of CR 27 Other than initial assessment of damage, no work has been started on this section of road. Full Closure 06/17/14 8:26 AM
31D
CR 31D
CR 22H End Area around bridge was backfilled by contractor. Pioneered single lane Full Closure 06/17/14 8:27 AM
43
CR 43 (Devils Gulch) from US 34 (Drake)
US 34 (at Drake) CR 61 (H Bar G road) The road is open full time to general traffic and there are no travel restrictions in place. For Project Summary information: http://larimer.org/engineering/PROJECTS/Stat9386.htm or visit http:www.lcr43.com Primitive two lane Recently Opened 09/29/14 7:29 AM
47
CR 47 (Big Elk Meadows)
US 36 County Line Debris has been cleared, washouts repaired, road base hauled in and culverts installed. Road is now open to general traffic. Please use caution still. Primitive two lane Recently Opened 09/29/14 7:31 AM
59
CR 59
County Line End of County Maintenance Local Access established. Pioneered single lane Restricted Access Only 06/17/14 8:29 AM
63
CR 63 (Fish Creek Rd)
US 36 Saddleback Lane Fish Creek Road now has two lanes open all the way from Hwy 36 to Hwy 7. The road is open full time to general traffic and there are no travel restrictions in place. The bridge and road work in the area around Little Valley is nearly complete. The temporary alignment of Little Valley Road on private property has been removed. Primitive two lane Recently Opened 08/05/14 1:21 PM
69B
CR 69B (Tunnel Road
Big Thompson River Bridge End of Road Completed Road went from a full closure to a one lane to now a two lane road. Work was done to backfill washouts and flood debris was removed. Crews have completed mitigation of the small slide that occurred post-flood. Primitive two lane Recently Opened 07/29/14 2:46 PM

Work Planned

Road number
Road name
From To Planned project start date Planned work Current road condition Closure type Last updated
22H
CR 22H (Part 1)
US 34 9597 CR 22H No repairs needed from initial flood on this section. All-weather surface Restricted Access Only 06/17/14 8:22 AM
22H
CR 22H (Part 2)
9597 CR 22H CR 29 Work is yet to be scheduled for this section of road. Local access has been established. There is road damage and the approach to the bridge over the Big Thompson River is damaged. Pioneered single lane Full Closure 06/17/14 8:23 AM
27
CR 27 (Buckhorn/Stove Praire Rd)
18000 Buckhorn Rd Ohana Way 0-15 days Work from 18000 Buckhorn Rd to Ohana Way will not occur until June 2014. This work will require significant design and repair work. This will be a hard closure for 2014. A determination has been made to NOT re-align the roadway out of the narrows. Design on the reconstruction of the roadway in much the same location as it was before is in process. Newsletter: http://larimer.org/engineering/cr_27.pdf or Project sheet: http://www.larimer.org/engineering/projects/Stat9323.htm Full Closure 09/29/14 7:34 AM
29
CR 29
approx. 1 mile north Hwy 34 approx. 2 miles SW of CR 27 Bridge is still standing, road is washed out leading up to the bridge on both sides. Repair work has not been scheduled for this section of road. Full Closure 06/17/14 8:26 AM
31D
CR 31D
CR 22H End Possible girder damage to bridge. Full Closure except very limited access. Further work has not been scheduled for this section. Pioneered single lane Full Closure 06/17/14 8:27 AM
43
CR 43 (Devils Gulch) from US 34 (Drake)
US 34 (at Drake) CR 61 (H Bar G road) 0-15 days Temporary repairs have been completed on this road. Travel Delays are possible in this area. Planning and design has begun for permanent repairs. Primitive two lane Recently Opened 09/29/14 7:29 AM
47
CR 47 (Big Elk Meadows)
US 36 County Line 0-15 days 12/13- Road now open to general traffic with no restrictions. For permanent repair information please visit http://www.larimer.org/engineering/projects/Stat9332.htm Primitive two lane Recently Opened 09/29/14 7:31 AM
59
CR 59
County Line End of County Maintenance No repair work currently scheduled for this road section. Pioneered single lane Restricted Access Only 06/17/14 8:29 AM
63
CR 63 (Fish Creek Rd)
US 36 Saddleback Lane 0-15 days Permanent work yet to be done. For Project Summary information: http://larimer.org/engineering/PROJECTS/Stat9339.htm Primitive two lane Recently Opened 08/05/14 1:21 PM