DRAINAGE IMPROVEMENTS ON HOLD

Project Number 8034
(County Road 68 & County Road 9 Intersection)

Last Updated: September 19, 2014

SCOPE OF WORK

  • Drainage improvements at intersection to direct storm water from northwest towards the southeast to Box Elder Creek.


  • Re-alignment of County Road 68 across intersection.

Project Budget: $165,000


PROJECT STATUS

The preliminary design has been completed. Acquisition of a minimal amount of right of way and final design is currently on hold until funding is secured for the project.

CONTACT

Kyle Arend, Project Manager
(970) 498-5734