POUDRE RIVER TRAIL TO BE EXTENDED SOUTH OF HARMONY ROAD

Project Number 5028
(Poudre River Trail)

Last Updated: April 15, 2015

SCOPE OF WORK

This joint project with the Town of Timnath consists of constructing a concrete trail from the end of the recently completed trail just north of Harmony Road (The Gateway Trailhead), south and east to Stonefly Drive in the planned Town Center just east of County Road 3F.

Project Budget: $600,000


PROJECT STATUS

Noraa Concrete Inc. began work March 9th. A parking lot at the Gateway Trailhead has been added to the work. The trail and parking lot should be open by the end of June.


CONTACT

Joe Temple, Project Manager
(970) 498-5717
Send e-mail