STOVE PRAIRIE ROAD TO BE REALIGNED

Project Number 299
(County Road 27 Realignment)

Last Updated: June 15, 2012

SCOPE OF WORK

A federal aid safety enhancement grant has been obtained for the realignment of a short segment of Stove Prairie Road (County Road 27) at a steeply graded S-curve between Stove Prairie and the Poudre Canyon.

Project Budget: $400,000


PROJECT STATUS

Bids were opened March 1st - Connell Resources Inc was awarded the work on the basis of their low bid of $363,529.00.

Construction is complete.


CONTACT

Joe Temple, Project Manager
(970) 498-5717
Send e-mail