DEVIL'S GULCH ROAD CULVERT REPLACEMENTS PLANNED

Project Number 297
(CR 43 Culvert Replacements)

Last Updated: November 16, 2012

SCOPE OF WORK

Replace culverts on CR 43 (Devil's Gulch Road) near the MacGregor Ranch Road and just east of the switchbacks. About 800 feet of CR 43 (the sharp curve at McGregor Ranch) will be slightly realigned.

Project Budget: $400,000

PROJECT STATUS

All work is complete.

CONTACT

Joe Temple, Project Manager
(970) 498-5717